The semi-finished components are ready

Precious sheets
The 5mm and 4mm sheets, cut, drilled, and folded according to the design, have arrived at the shipyard. All elements are coded and listed on an online database to be checked at the construction site before starting the assembly. It is the last order the supplier could fulfill before the supply block due to the war conflict. The material had already undergone a 90% increase, and the constant demand with a shrinking supply due to war-related reasons continues to drive prices higher. That's the free market.

Foratura per riferimenti di montaggio

Ogni pezzo ha un'etichettatura con il riferimento alla tavola progettuale

Particolare della piegatura e della giunzione a 110°. Tavola P1504-110

Fogli di lamiera per il rivestimento di coperta

Foratura per i chiodi di saldatura

Particolare del raggio di piega

Verifica al ricevimento della merce